- Scheme area of project is 131.96 acres.
- All the mandatory clearances have been obtained such as CLU, RERA & Environment Clearance.
- As requested by PSPCL, an area of 8 acres (At least 4 acres as per agreement) of land has been earmarked for PSPCL for setting up of 220 KV Substation.
- Department of Irrigation has assured to meet the entire requirement with canal water 2.5 MLD (2500 KLD) for the Park.
- 80 Acres of land has been allotted to M/s Sanathan Textiles Ltd.
- Work of construction of 4 lane approach road is in progress and will be completed by Oct, 2022.
- Time Line:
- Date of start- 01st January, 2022.
- Completion period- 20 Months.
- Estimated Date of Completion- 31st August, 2023